Kalpasar project status in 2026: what is approved, what is still a plan and what it means for Dholera

Updated 11 November 2026. Compiled by the dholeraSTOP desk from the sources listed at the end of this page.

Kalpasar is still a plan. On 27 July 2026 the Jal Shakti minister told the Rajya Sabha that the Detailed Project Report is at an advanced stage of finalisation. On 21 May 2026 the project applied to start detailed environmental studies, at a reported cost of Rs 1,33,246 crore. If clearances come on schedule, construction would begin in May 2028. The sources we read do not mention Dholera. Status as of 13 November 2026.

Kalpasar in numbers, with the source for each

ItemWhat the record saysSource and dateHow firm
What it isA 60.13 km dyke from Kardej village in Bhavnagar district to Paniyadra village in Bharuch district, 26.7 km of it in the sea, forming a coastal freshwater reservoir of 7,807 million cubic metresDeshGujarat, 27 May 2026Regional newsroom reporting the application
Reported costRs 1,33,246 crore, of which the dyke alone is over Rs 54,000 crore. The 2022 pre-feasibility figure was Rs 1,00,200 croreDeshGujarat, 27 May 2026Estimate in an application, not a sanctioned budget
PurposesIrrigation for about 9.99 lakh hectares in 42 talukas of nine Saurashtra districts, drinking and industrial water, a 16-lane road and four-lane railway on a 130 m corridor, and wind-solar power of 2,500 million units a yearDeshGujarat, 27 May 2026Design intent
Report stageDetailed Project Report at an advanced stage of finalisation, with Indo-Dutch technical cooperation on coastal engineering, hydraulic modelling and salinity managementWritten reply in the Rajya Sabha, 27 July 2026, via NewKeralaMinisterial statement
Clearance stepOn 21 May 2026 the Kalpasar Department applied to the Environment Ministry to begin detailed environmental studies, with NEERI as consultantDeshGujarat, 27 May 2026Application filed, not clearance granted
TimelineConstruction from May 2028 if clearances are on schedule, completion targeted for late 2035DeshGujarat, 27 May 2026Target
DholeraNot mentioned in either sourceBoth sources read 13 November 2026Negative finding

Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.

What is Kalpasar?

Kalpasar is a proposal to close the northern Gulf of Khambhat with a dyke so that river water collects behind it as a freshwater reservoir. The planned alignment runs between Bhavnagar and Bharuch districts. The reservoir would feed irrigation and drinking water mainly for Saurashtra, and the dyke top would carry a road and railway.

How far along is it?

The step that has happened is an application for detailed environmental studies, filed on 21 May 2026, and a ministerial statement on 27 July 2026 that the project report is nearly final. Neither is a sanction of funds or a start of work. Construction is a target for May 2028.

What does it cost and who pays?

The estimate in the application is Rs 1,33,246 crore, up from about Rs 1,00,200 crore in an earlier report. The reports we read do not give a funding split, so we do not state one.

Does Kalpasar affect Dholera?

Dholera SIR is on the western shore of the same Gulf of Khambhat, but neither source we read links Kalpasar to Dholera, and we found no official statement of an effect on Dholera land, drainage or water supply. A project that is still at the study stage should not be treated as a reason for any plot decision. Dholera's own works are tracked on our pages for infrastructure projects and connectivity upgrades.

How does it connect to tides and drainage?

Tidal and coastal engineering is one of the Dutch cooperation areas named in the ministerial reply. Dholera's own drainage design, reported works and gaps are in our page on Dholera storm water drainage.

What should a reader watch for next?

  1. Publication of the final Detailed Project Report.
  2. The Environment Ministry's decision on the terms of reference for the studies.
  3. A Cabinet or state sanction with a funding split.
  4. A tender for the first package.

No price movement for any plot is implied by any of these steps.

What this page cannot tell you

This page rests on two news reports of a government application and a ministerial reply, read on 13 November 2026, and not on the Detailed Project Report, which we could not find published. It cannot say how Kalpasar would affect Dholera.

Questions people ask

What is the Kalpasar project?

A proposed 60.13 km dyke between Kardej in Bhavnagar district and Paniyadra in Bharuch district, creating a coastal freshwater reservoir of 7,807 million cubic metres with a road and railway on top.

What is the status of the Kalpasar project in 2026?

It is at the planning stage. The Detailed Project Report is at an advanced stage of finalisation as stated in the Rajya Sabha on 27 July 2026, and an application for detailed environmental studies was filed on 21 May 2026.

How much will Kalpasar cost?

The application filed on 21 May 2026 reports Rs 1,33,246 crore. That is an estimate and not a sanctioned budget.

When will Kalpasar be built?

Construction is targeted from May 2028 if clearances arrive on schedule, with completion targeted for late 2035, as reported on 27 May 2026.

Will Kalpasar benefit Dholera?

The reports we read do not mention Dholera, so we cannot say. Treat any broker claim of a Kalpasar effect on plot prices as unsupported unless it cites an official document.

Read next

Sources

  1. DeshGujarat, Gujarat seeks environmental clearance for Rs 1.33 lakh crore Kalpasar project (27 May 2026)
  2. NewKerala, Centre details Indo-Dutch push to finalise Kalpasar DPR (Rajya Sabha reply) (27 July 2026)
  3. DeshGujarat, Kalpasar project to link Bhavnagar and Bharuch through 60 km dyke route (29 May 2026)