Updated 11 November 2026. Compiled by the dholeraSTOP desk from the sources listed at the end of this page.
Kalpasar is still a plan. On 27 July 2026 the Jal Shakti minister told the Rajya Sabha that the Detailed Project Report is at an advanced stage of finalisation. On 21 May 2026 the project applied to start detailed environmental studies, at a reported cost of Rs 1,33,246 crore. If clearances come on schedule, construction would begin in May 2028. The sources we read do not mention Dholera. Status as of 13 November 2026.
| Item | What the record says | Source and date | How firm |
|---|---|---|---|
| What it is | A 60.13 km dyke from Kardej village in Bhavnagar district to Paniyadra village in Bharuch district, 26.7 km of it in the sea, forming a coastal freshwater reservoir of 7,807 million cubic metres | DeshGujarat, 27 May 2026 | Regional newsroom reporting the application |
| Reported cost | Rs 1,33,246 crore, of which the dyke alone is over Rs 54,000 crore. The 2022 pre-feasibility figure was Rs 1,00,200 crore | DeshGujarat, 27 May 2026 | Estimate in an application, not a sanctioned budget |
| Purposes | Irrigation for about 9.99 lakh hectares in 42 talukas of nine Saurashtra districts, drinking and industrial water, a 16-lane road and four-lane railway on a 130 m corridor, and wind-solar power of 2,500 million units a year | DeshGujarat, 27 May 2026 | Design intent |
| Report stage | Detailed Project Report at an advanced stage of finalisation, with Indo-Dutch technical cooperation on coastal engineering, hydraulic modelling and salinity management | Written reply in the Rajya Sabha, 27 July 2026, via NewKerala | Ministerial statement |
| Clearance step | On 21 May 2026 the Kalpasar Department applied to the Environment Ministry to begin detailed environmental studies, with NEERI as consultant | DeshGujarat, 27 May 2026 | Application filed, not clearance granted |
| Timeline | Construction from May 2028 if clearances are on schedule, completion targeted for late 2035 | DeshGujarat, 27 May 2026 | Target |
| Dholera | Not mentioned in either source | Both sources read 13 November 2026 | Negative finding |
Download this table (CSV). Last checked 11 November 2026. Free to quote with a link to this page.
Kalpasar is a proposal to close the northern Gulf of Khambhat with a dyke so that river water collects behind it as a freshwater reservoir. The planned alignment runs between Bhavnagar and Bharuch districts. The reservoir would feed irrigation and drinking water mainly for Saurashtra, and the dyke top would carry a road and railway.
The step that has happened is an application for detailed environmental studies, filed on 21 May 2026, and a ministerial statement on 27 July 2026 that the project report is nearly final. Neither is a sanction of funds or a start of work. Construction is a target for May 2028.
The estimate in the application is Rs 1,33,246 crore, up from about Rs 1,00,200 crore in an earlier report. The reports we read do not give a funding split, so we do not state one.
Dholera SIR is on the western shore of the same Gulf of Khambhat, but neither source we read links Kalpasar to Dholera, and we found no official statement of an effect on Dholera land, drainage or water supply. A project that is still at the study stage should not be treated as a reason for any plot decision. Dholera's own works are tracked on our pages for infrastructure projects and connectivity upgrades.
Tidal and coastal engineering is one of the Dutch cooperation areas named in the ministerial reply. Dholera's own drainage design, reported works and gaps are in our page on Dholera storm water drainage.
No price movement for any plot is implied by any of these steps.
This page rests on two news reports of a government application and a ministerial reply, read on 13 November 2026, and not on the Detailed Project Report, which we could not find published. It cannot say how Kalpasar would affect Dholera.
A proposed 60.13 km dyke between Kardej in Bhavnagar district and Paniyadra in Bharuch district, creating a coastal freshwater reservoir of 7,807 million cubic metres with a road and railway on top.
It is at the planning stage. The Detailed Project Report is at an advanced stage of finalisation as stated in the Rajya Sabha on 27 July 2026, and an application for detailed environmental studies was filed on 21 May 2026.
The application filed on 21 May 2026 reports Rs 1,33,246 crore. That is an estimate and not a sanctioned budget.
Construction is targeted from May 2028 if clearances arrive on schedule, with completion targeted for late 2035, as reported on 27 May 2026.
The reports we read do not mention Dholera, so we cannot say. Treat any broker claim of a Kalpasar effect on plot prices as unsupported unless it cites an official document.